Fibre cut on the Arelion path out of AMS

网络——转接与对等互联——AMS

时间线

  1. 已解决

    Full redundancy in AMS restored at 01:30 UTC. Duration of the reduced-redundancy state: 4 h 26 min. No machine lost connectivity at any point; this is what the second carrier is for.

  2. 观察中

    The splice is complete and the Arelion link is back at full light level. We are re-enabling it gradually and watching error counters.

  3. 已确定原因

    Arelion has confirmed a fibre cut caused by third-party roadworks about 9 km from the site. A splice crew has been dispatched. We are operating on the second carrier plus the exchange for the duration, with headroom for peak traffic.

  4. 调查中

    The Arelion uplink in AMS went down at 21:04 UTC. Traffic failed over to Lumen and NL-ix within seconds; capacity is reduced but no machine is unreachable. Arelion reports a loss of light on the metro fibre.