Fibre cut on the Arelion path out of AMS
Réseau — transit et peering — AMS
Chronologie
-
Résolu
Full redundancy in AMS restored at 01:30 UTC. Duration of the reduced-redundancy state: 4 h 26 min. No machine lost connectivity at any point; this is what the second carrier is for.
-
Sous surveillance
The splice is complete and the Arelion link is back at full light level. We are re-enabling it gradually and watching error counters.
-
Cause identifiée
Arelion has confirmed a fibre cut caused by third-party roadworks about 9 km from the site. A splice crew has been dispatched. We are operating on the second carrier plus the exchange for the duration, with headroom for peak traffic.
-
Investigation en cours
The Arelion uplink in AMS went down at 21:04 UTC. Traffic failed over to Lumen and NL-ix within seconds; capacity is reduced but no machine is unreachable. Arelion reports a loss of light on the metro fibre.
Les heures sont affichées dans votre fuseau horaire ().
Pages liées
- État du serviceÉtat en direct des composants et centres de données gpuserver.io, sondés toutes les 60 s depuis cinq villes : disponibilité sur 90 jours et incidents depuis 2022.
- Historique des incidentsChaque incident et fenêtre de maintenance sur gpuserver.io depuis septembre 2022, mois par mois, avec chronologie et revue post-incident.
- Accord de niveau de serviceL’engagement de 99,9 % : la définition d’une panne, la mesure externe, cinq minutes de durée d’engagement rendues par minute perdue, et les exclusions en détail.
- RéseauPorts sans compteur jusqu’à 25 Gbit/s, deux opérateurs et un IX par site, filtrage DDoS permanent, IPv6 routé — et quatre choses que nous n’offrons pas, en clair.