Annual cooling system service — ZRH
电力与散热——ZRH
计划安排
The facility services the cooling plant in ZRH: filters, refrigerant levels, pump inspection. Units are serviced one at a time; the room stays within its temperature envelope on the remaining units. GPU clocks are not expected to change. We monitor inlet temperatures throughout and will pause the work if any row exceeds target.
时间线
-
已完成
All units serviced. Inlet temperatures stayed within 2 °C of target throughout.
-
进行中
Service has started on the first cooling unit. Inlet temperatures are at target.
-
已排期
The facility services the cooling plant in ZRH: filters, refrigerant levels, pump inspection. Units are serviced one at a time; the room stays within its temperature envelope on the remaining units. GPU clocks are not expected to change. We monitor inlet temperatures throughout and will pause the work if any row exceeds target.