Cooling alarm in YUL, row D; some nodes thermally throttled

Питание и охлаждение — YUL

Хронология

  1. Устранено

    Row D is back at target temperature and no GPU is throttling. Duration: 36 minutes. Affected workloads ran slower during the event but were not interrupted.

  2. Наблюдение

    The tripped unit is back in service and inlet temperatures are falling. GPU clocks are returning to normal.

  3. Причина установлена

    One of the two CRAC units serving row D tripped on a pressure alarm. The remaining unit is holding the row a few degrees above target. The facility has an engineer on the unit.

  4. Идёт расследование

    Inlet temperatures in row D of YUL rose above the alert threshold at 20:12 UTC. GPUs on 17 machines in that row have reduced their clocks to stay within limits. Machines remain reachable and workloads continue at lower performance.