Major Resolved Review published

PDU fault in rack AMS-B06

Power & cooling — AMS · Out-of-band management — AMS

Timeline

  1. Resolved

    Every machine in rack B06 has been up since 02:52 UTC. Duration: 16 minutes. The PDU is being replaced; the 8 machines that lost power receive the SLA extension automatically. Data on local disks is intact; the machines simply rebooted.

  2. Identified

    The A-side PDU in rack B06 failed with a breaker fault. The 8 machines that rebooted are the ones whose B-side supply was not seated correctly after a recent hardware change. All are powered from the B-side now and are booting.

  3. Investigating

    8 machines in rack B06 of AMS lost power at 02:36 UTC. Machines in the rack are dual-fed, but these 8 rebooted when one PDU failed. Engineers are at the rack.

Post-incident review ·

What happened, and what changed

Cause

The A-side PDU in AMS-B06 suffered a breaker fault. Every machine in the rack has two power supplies on separate feeds, but on 8 of them the B-side cord had been left partially seated during a hardware change the previous week, so they lost power when the A side went.

Impact

8 machines rebooted and were unavailable for 16 minutes. No data was lost; the machines came back to the state they were installed in, with local disks intact.

What we changed

  • Every hardware change now ends with a power-redundancy test: each feed is dropped in turn and the machine must stay up.
  • The faulty PDU model is being phased out across the fleet.
  • Term extensions were applied to the 8 machines the same day.