Facility generator and transfer-switch test — YUL
電源・冷却 — YUL
予定内容
The facility runs its periodic test of the generators and automatic transfer switches in YUL. The site is transferred to generator and back under load. The UPS covers the transfers; machines do not notice. We post it because the site is on a single source for a few minutes during each transfer.
タイムライン
-
完了
Test complete. YUL is back on utility power; both transfers were clean.
-
実施中
The test is under way. YUL is on generator; the UPS carried the transfer with no disturbance.
-
予定
The facility runs its periodic test of the generators and automatic transfer switches in YUL. The site is transferred to generator and back under load. The UPS covers the transfers; machines do not notice. We post it because the site is on a single source for a few minutes during each transfer.
時刻はお使いのタイムゾーン()で表示されます。
関連ページ
- サービスステータスgpuserver.ioの全コンポーネントと全データセンターのライブステータス。5都市から60秒ごとに監視プローブで測定し、90日間の稼働率と2022年以降のインシデントログを掲載。
- インシデント履歴gpuserver.ioで2022年9月の監視開始以降に発生した、すべてのインシデントとメンテナンス時間帯を月別に掲載。タイムラインと事後レビューも収録しています。
- サービスレベル契約稼働率99.9%の約束:何がダウンタイムとみなされるか、外部からどう測定するか、失った1分につき契約期間を5分延長する仕組み、そして適用除外の全内容。
- ネットワーク最大25Gbit/sの無制限ポート、拠点ごとに2つのキャリアと1つのIX、常時稼働のDDoSフィルタリング、ルーテッドIPv6。そして、提供しない4つのことを最初に明示します。