Facility generator and transfer-switch test — STO
Güç ve soğutma — STO
Ne planlanıyor
The facility runs its periodic test of the generators and automatic transfer switches in STO. The site is transferred to generator and back under load. The UPS covers the transfers; machines do not notice. We post it because the site is on a single source for a few minutes during each transfer.
Zaman çizelgesi
-
Tamamlandı
Test complete. STO is back on utility power; both transfers were clean.
-
Sürüyor
The test is under way. STO is on generator; the UPS carried the transfer with no disturbance.
-
Planlandı
The facility runs its periodic test of the generators and automatic transfer switches in STO. The site is transferred to generator and back under load. The UPS covers the transfers; machines do not notice. We post it because the site is on a single source for a few minutes during each transfer.
Saatler, saat diliminizde () gösterilir.
İlgili sayfalar
- Hizmet durumugpuserver.io'nun her bileşeni ve veri merkezi, beş şehirden 60 saniyede bir yoklanır; 90 günlük kullanılabilirlik ve 2022'den beri olay logu burada yer alır.
- Olay geçmişigpuserver.io'da izlemenin başladığı Eylül 2022'den bu yana yaşanan her olay ve bakım penceresi, ay ay, zaman çizelgesi ve olay sonrası incelemesiyle birlikte.
- Hizmet seviyesi sözleşmesi%99,9 taahhüdü: neyin kesinti sayıldığı, dışarıdan nasıl ölçüldüğü, kaybedilen her dakika için beş dakika süre iadesi ve istisnaların tamamı.
- Ağ25 Gbit/s'e kadar sayaçsız portlar, site başına iki operatör ve bir IX, sürekli DDoS filtreleme, yönlendirilen IPv6 — ve baştan belirtilen, sunmadığımız dört şey.