Facility generator and transfer-switch test — STO

Alimentación y refrigeración — STO

Qué está previsto

The facility runs its periodic test of the generators and automatic transfer switches in STO. The site is transferred to generator and back under load. The UPS covers the transfers; machines do not notice. We post it because the site is on a single source for a few minutes during each transfer.

Cronología

  1. Completado

    Test complete. STO is back on utility power; both transfers were clean.

  2. En curso

    The test is under way. STO is on generator; the UPS carried the transfer with no disturbance.

  3. Programado

    The facility runs its periodic test of the generators and automatic transfer switches in STO. The site is transferred to generator and back under load. The UPS covers the transfers; machines do not notice. We post it because the site is on a single source for a few minutes during each transfer.

Iniciar sesión

Consola, facturas y acceso fuera de banda.

¿Aún no tiene cuenta?

No hay un registro aparte. Su cuenta se crea mientras realiza su primer pedido — elige el correo electrónico y la contraseña en el paso de pago, y la consola está abierta para cuando lo está la máquina.

Configurar un servidor

Language