Core router software upgrade — AMS
Rede — trânsito e peering — AMS
O que está planejado
We will upgrade the operating system on the two core routers in AMS, one after the other. Each router is drained before it reloads, so traffic stays on the other one. Expect up to 60 seconds of reduced redundancy per router while its BGP sessions reconverge; no machine should lose connectivity. Out-of-band access is unaffected.
Linha do tempo
-
Concluída
Both core routers in AMS are on the new release and carrying traffic. No connectivity was lost during the window.
-
Em andamento
We need about 25 more minutes than announced. The work is proceeding normally; the window is extended by that amount.
-
Em andamento
Maintenance has started. The first core router in AMS has been drained and is reloading.
-
Agendada
We will upgrade the operating system on the two core routers in AMS, one after the other. Each router is drained before it reloads, so traffic stays on the other one. Expect up to 60 seconds of reduced redundancy per router while its BGP sessions reconverge; no machine should lose connectivity. Out-of-band access is unaffected.
Os horários são mostrados no seu fuso horário ().
Páginas relacionadas
- Status do serviçoStatus de cada componente e centro de dados do gpuserver.io, sondados a cada 60s em cinco cidades, com disponibilidade de 90 dias e log de incidentes desde 2022.
- Histórico de incidentesTodos os incidentes e janelas de manutenção em gpuserver.io desde setembro de 2022, mês a mês, com linha do tempo e revisão pós-incidente.
- Acordo de nível de serviçoO compromisso de 99,9%: o que conta como indisponibilidade, como é medido de fora, cinco minutos de prazo devolvidos por minuto perdido, e as exclusões por completo.
- RedePortas sem contador até 25 Gbit/s, duas operadoras e um IX por site, filtragem DDoS sempre ativa, IPv6 roteado — e as quatro coisas que não oferecemos, já ditas.