Core router software upgrade — AMS
Red — tránsito y peering — AMS
Qué está previsto
We will upgrade the operating system on the two core routers in AMS, one after the other. Each router is drained before it reloads, so traffic stays on the other one. Expect up to 60 seconds of reduced redundancy per router while its BGP sessions reconverge; no machine should lose connectivity. Out-of-band access is unaffected.
Cronología
-
Completado
Both core routers in AMS are on the new release and carrying traffic. No connectivity was lost during the window.
-
En curso
We need about 25 more minutes than announced. The work is proceeding normally; the window is extended by that amount.
-
En curso
Maintenance has started. The first core router in AMS has been drained and is reloading.
-
Programado
We will upgrade the operating system on the two core routers in AMS, one after the other. Each router is drained before it reloads, so traffic stays on the other one. Expect up to 60 seconds of reduced redundancy per router while its BGP sessions reconverge; no machine should lose connectivity. Out-of-band access is unaffected.
Las horas se muestran en su zona horaria ().
Páginas relacionadas
- Estado del servicioEstado en vivo de gpuserver.io: componentes y centros de datos sondeados cada 60 s desde 5 ciudades, con disponibilidad de 90 días e incidentes desde 2022.
- Historial de incidentesTodos los incidentes y ventanas de mantenimiento de gpuserver.io desde septiembre de 2022, mes a mes, con cronología y revisión posterior al incidente.
- Acuerdo de nivel de servicioEl compromiso del 99,9 %: qué cuenta como inactividad, cómo se mide desde fuera, cinco minutos de plazo por cada minuto perdido, y las exclusiones completas.
- RedPuertos sin contador hasta 25 Gbit/s, dos operadores y un IX por sede, filtrado DDoS permanente, IPv6 enrutado — y las cuatro cosas que no ofrecemos, dichas ya.