Manutenção Concluída

UPS battery replacement — YUL

Energia e refrigeração — YUL

O que está planejado

The facility replaces the battery strings in one UPS module in YUL. The module is taken out of the parallel set for the work; the remaining modules carry the full load with redundancy reduced by one. No machine loses power. Scheduled during the day so that the facility's electrical team is fully staffed.

Linha do tempo

  1. Concluída

    The module is back in the set with new batteries and has completed its charge test.

  2. Em andamento

    The UPS module is out of the set and the batteries are being swapped. All machines are on the remaining modules.

  3. Agendada

    The facility replaces the battery strings in one UPS module in YUL. The module is taken out of the parallel set for the work; the remaining modules carry the full load with redundancy reduced by one. No machine loses power. Scheduled during the day so that the facility's electrical team is fully staffed.

Entrar

Console, faturas e acesso fora de banda.

Ainda não tem uma conta?

Não existe cadastro separado. Sua conta é criada enquanto você faz seu primeiro pedido — você escolhe o e-mail e a senha na etapa de pagamento, e o console já está aberto quando a máquina estiver pronta.

Configurar um servidor

Language