Annual cooling system service — AMS
Power & cooling — AMS
What is planned
The facility services the cooling plant in AMS: filters, refrigerant levels, pump inspection. Units are serviced one at a time; the room stays within its temperature envelope on the remaining units. GPU clocks are not expected to change. We monitor inlet temperatures throughout and will pause the work if any row exceeds target.
Timeline
-
Completed
All units serviced. Inlet temperatures stayed within 2 °C of target throughout.
-
In progress
Service has started on the first cooling unit. Inlet temperatures are at target.
-
Scheduled
The facility services the cooling plant in AMS: filters, refrigerant levels, pump inspection. Units are serviced one at a time; the room stays within its temperature envelope on the remaining units. GPU clocks are not expected to change. We monitor inlet temperatures throughout and will pause the work if any row exceeds target.
Times are shown in your time zone ().
Related pages
- Service statusLive status of every gpuserver.io component and data centre, probed every 60 seconds from five cities, with 90-day uptime and the incident log since 2022.
- Incident historyEvery incident and maintenance window on gpuserver.io since monitoring began in September 2022, month by month, with its timeline and post-incident review.
- Service level agreementThe 99.9% commitment: what counts as downtime, how it is measured from outside, five minutes of term back per minute lost, and the exclusions in full.
- NetworkUnmetered ports up to 25 Gbit/s, two carriers and an IX per site, always-on DDoS filtering, routed IPv6 — and the four things we do not offer, stated up front.